The project improvements include:
· Asphalt pavement
· Storm sewer repairs
· Sanitary sewer repairs
· Concrete curb & gutter repair and replacement
. Parkway restoration

Project Timeline:
May 2013 – Start of Construction
October 2013 – End of Construction

Streets scheduled for improvements include:
1. Hammersmith Lane: Potter Road to Franklin Drive
2. Glenlake Drive: Warrington Court to North Gate
3. Stratford Lane: Glenlake Drive to South End
4. Inverness Lane: Winchester Lane to Glenlake Drive
5. Winchester Lane: Inverness Lane to Glenlake Drive
6. Longmeadow Drive: Glenview Road to Lake Avenue
7. Crestwood Lane: Longmeadow to West End
8. Canterbury Lane: East Lake Avenue to South End
9. Sanford Lane: East Lake Avenue to Sanford Court
10. Longmeadow Drive: East Lake Avenue to Bellwood Lane
11. Bellwood Lane: Greenwood Road to Executive Lane
12. Ralmark Lane: Bellwood Lane to Longmeadow Drive
13. Woodmere Lane: Glenview Road to South End

Friday, August 30, 2013

Pavement Markings Completed

Last week, pavement markings were installed on various streets. 

Next week, sod installation may begin depending on weather conditions. Otherwise, the contractor will wait until the weather is cooler for more favorable growing conditions.

The roadway resurfacing of Longmeadow Drive, Ralmark Lane, and Bellwood Lane will be completed following the completion of the other work on-going along those roadways.

Thank you for your patience and understanding during the construction operations.

Monday, August 26, 2013

Pavement Markings at Central and Shermer Completed

Last week, the landscaping sub-contractor performed grading and installation of topsoil and seed at various sites throughout the project. The pavement marking sub-contractor also completed the pavement markings at the intersection of Central Road and Shermer Road. Asphalt driveways along Sanford, Canterbury, and Woodmere were also restored this past week.

Next week, no work is anticipated to be performed on-site.

Installation of sod will not be completed until after the Labor Day weekend in anticipation of more favorable growing conditions. The other remaining items to be completed include pavement striping at various locations and a few minor repairs.

The roadway resurfacing of Longmeadow Drive, Ralmark Lane, and Bellwood Lane will be completed following the completion of the other work on-going along those roadways.

Thank you for your patience and understanding during the construction operations.

Monday, August 19, 2013

Landscape Restoration On-Going

Last week, the landscaping sub-contractor performed some installation and grading of topsoil and seed at various sites throughout the project. The contractor also completed the repairs at the intersection of Central Road and Shermer Road.

Next week, the contractor is scheduled to complete the remaining asphalt driveway restorations, landscape restorations, and perform pavement markings around the various project sites.

The roadway portion of the project is now on hold until other underground utility work around the Village is completed.

Thank you for your patience and understanding during the construction operations.

Monday, August 12, 2013

Roadway Work Completed Until Other Work is Completed

Last week, Arrow Road completed the asphalt paving of Woodmere Lane. The contractor also performed landscape restorations throughout the project within utility trenches and behind concrete curb & gutter that was previously replaced.

The contractor will complete the remaining asphalt driveway restorations in the near future.

The roadway portion of the project is now on hold until other underground utility work around the Village is completed.

Thank you for your patience and understanding during the construction operations.

Friday, August 2, 2013

Asphalt Paving on Canterbury and Sanford Completed

Last week, Arrow Road completed grading of the existing base and asphalt paving of binder and surface layers along Sanford and Canterbury.

Next week, Arrow Road is scheduled to pave the asphalt surface layer on Woodmere Lane.

The contractor will also begin landscape and driveway restorations along the project site in the near future.

Once the paving on Woodmere Lane is complete, the roadwork portion of the project will be on hold until other underground utility work around the Village is completed.

Thank you for your patience and understanding during the construction operations.