The project improvements include:
· Asphalt pavement
· Storm sewer repairs
· Sanitary sewer repairs
· Concrete curb & gutter repair and replacement
. Parkway restoration

Project Timeline:
May 2013 – Start of Construction
October 2013 – End of Construction

Streets scheduled for improvements include:
1. Hammersmith Lane: Potter Road to Franklin Drive
2. Glenlake Drive: Warrington Court to North Gate
3. Stratford Lane: Glenlake Drive to South End
4. Inverness Lane: Winchester Lane to Glenlake Drive
5. Winchester Lane: Inverness Lane to Glenlake Drive
6. Longmeadow Drive: Glenview Road to Lake Avenue
7. Crestwood Lane: Longmeadow to West End
8. Canterbury Lane: East Lake Avenue to South End
9. Sanford Lane: East Lake Avenue to Sanford Court
10. Longmeadow Drive: East Lake Avenue to Bellwood Lane
11. Bellwood Lane: Greenwood Road to Executive Lane
12. Ralmark Lane: Bellwood Lane to Longmeadow Drive
13. Woodmere Lane: Glenview Road to South End

Friday, June 28, 2013

Asphalt Paving of Various Roadways Continues

Last week, Arrow Road Inc., completed paving along Glenlake Drive, Stratford Lane, Winchester Lane, Inverness Lane, Hammersmith Lane, and Harrison Street. Arrow Road also removed pavement and paved Railroad Avenue parking stalls from Dewes Street to the south end, Indian Ridge Drive, Magnolia Street, Covert Road, Karen Lane, and Pick Lane.  The contractor also removed the pavement at the intersection of Central Road and Shermer Road, and along Robincrest Lane, Long Valley Road, and Ardmore Avenue.

Next week, Arrow Road will complete structure adjustments, patching, and paving along Central and Shermer, pave Robincrest Lane, Long Valley Road, and Ardmore Avenue.

The contractor will not be working on Thursday, July 4th and is not anticipating performing any work on-site on Friday July 5th.

Thank you for your patience during the construction operations.

Friday, June 21, 2013

Road Work Continues throughout the Village

Last week, DeVinci Construction finished underground storm sewer repairs and utility structure replacements on Canterbury Lane and Sanford Lane.  DeVinci Construction also performed a storm structure adjustment on Robincrest Lane and a storm structure reconstruction on Indian Ridge Drive. 

D’Land Construction finished installing concrete curb & gutter and sidewalk replacements along Hammersmith Lane, Glenlake Drive, Stratford Lane, Winchester Lane, and Inverness Lane.  D’land Construction also performed minor concrete curb & gutter replacements on Indian Ridge Drive, Magnolia Street, Covert Road, Karen Lane, Robincrest Lane, and at the Shermer Road and Central Road intersection. 

Arrow Road performed asphalt patching along Elmdale Road,  Old Willow Road, and Fir Street.  Arrow Road also performed 2” asphalt removal and replacement on Pleasant Lane, Kenilworth Lane, Highland Terrace, Wildwood Terrace, Roosevelt Avenue, Elmdale Road, Hammersmith Lane, Glenlake Drive, Stratford Lane, Winchester Lane, and Inverness Lane

Next week, D’Land Construction will perform concrete curb & gutter replacements along Sanford Lane and Canturbury Lane.  Residents affected by the curb work will be notified to be out of their driveways before this work begins.

Arrow Road will continue milling and paving various roadways throughout the Village. Residents affected by this work will be notified prior to the work starting.

Thank you for your patience during the construction operations.

Friday, June 14, 2013

Concrete Work started in Glen Lake Estates. Utility Repairs on Canterbury and Sanford

Last week, the contractor performed concrete curb & gutter replacements along Hammersmith Lane, Glenlake Drive, Stratford Lane, Winchester Lane, and Inverness Lane. The contractor completed storm sewer repairs on Hammersmith Lane and Winchester Lane.

Next week, the D’Land Construction will continue concrete curb & gutter and sidewalk replacements along Hammersmith Lane, Glenlake Drive, Stratford Lane, Winchester Lane, and  Inverness Lane.

Arrow Road will perform asphalt patching along Elmdale Road,  Old Willow Road, and Fir Street. The contractor will may also begin milling various roadways throughout the Village. Residents effected by this work will be notified prior the work starting.

The underground contractor will perform utilities repairs along Canterbury Lane from East Lake Avenue to the south end and along Sanford Lane. All other work along Canterbury Lane and Sanford Lane will be suspended until the PGA golf tournament is completed.

Thank you for your patience during the construction operations.

Friday, June 7, 2013

Concrete Curb & Gutter and Sidewalk Repairs to Begin

Last week, the contractor broke out concrete curb & gutter around structures for adjustments on all the roadways associated with the project and began performing structure adjustments in Glen Lake Estates neighborhood.

Next week, the contractor will begin concrete curb & gutter and sidewalk removal and replacements along Hammersmith Lane, Glenlake Drive, Stratford Lane, Winchester Lane, Inverness Lane, Sanford Lane, and Canterbury Lane. Structure adjustments will continue throughout the roadways within the project. The contractor will also complete the utility improvements along Hammersmith Lane and Winchester Lane.