The project improvements include:
· Asphalt pavement
· Storm sewer repairs
· Sanitary sewer repairs
· Concrete curb & gutter repair and replacement
. Parkway restoration

Project Timeline:
May 2013 – Start of Construction
October 2013 – End of Construction

Streets scheduled for improvements include:
1. Hammersmith Lane: Potter Road to Franklin Drive
2. Glenlake Drive: Warrington Court to North Gate
3. Stratford Lane: Glenlake Drive to South End
4. Inverness Lane: Winchester Lane to Glenlake Drive
5. Winchester Lane: Inverness Lane to Glenlake Drive
6. Longmeadow Drive: Glenview Road to Lake Avenue
7. Crestwood Lane: Longmeadow to West End
8. Canterbury Lane: East Lake Avenue to South End
9. Sanford Lane: East Lake Avenue to Sanford Court
10. Longmeadow Drive: East Lake Avenue to Bellwood Lane
11. Bellwood Lane: Greenwood Road to Executive Lane
12. Ralmark Lane: Bellwood Lane to Longmeadow Drive
13. Woodmere Lane: Glenview Road to South End

Friday, October 11, 2013

Curb & Replacement On-Going North of East Lake Avenue

This past week the concrete sub-contractor, D’Land Construction, removed the existing concrete curb & gutter on the north side of Bellwood Lane, west side of Longmeadow Drive, and south and east sides of Ralmark Lane. D’Land also begin installing the concrete curb & gutter in these areas.  The concrete work in these areas of the roadway will continue early next week with the completion of the concrete curb & gutter and concrete driveway installation.

Next week, the contractor will allow the newly installed concrete to cure. The contractor will then move the opposite sides of the street to begin concrete curb & gutter removal and replacement. Additional notification and parking restrictions will be provided when a firm schedule is determined.

All the roadways within the project limits, including Longmeadow Drive from Glenview Road to East Lake Avenue (area south of East Lake Avenue), Longmeadow Drive from East Lake Avenue to Bellwood Lane (area north of East Lake Avenue), Bellwood Lane from Executive Court to Greenwood Road, and Ralmark Lane from Bellwood Lane to Longmeadow Drive  will have the existing asphalt surface milled and repaved as part of this project. This work will not take place until after the concrete curb & gutter replacement north of East Lake Avenue are completed. We are currently working with the contractors to determine the exact start date for the roadway resurfacing, but we are anticipating the work will begin 2 to 3 weeks.

We continue to expression our gratitude for your patience during the construction operations. Your cooperation with the inconvenience associated with the concrete curb & gutter construction is greatly appreciated.