The project improvements include:
· Asphalt pavement
· Storm sewer repairs
· Sanitary sewer repairs
· Concrete curb & gutter repair and replacement
. Parkway restoration

Project Timeline:
May 2013 – Start of Construction
October 2013 – End of Construction

Streets scheduled for improvements include:
1. Hammersmith Lane: Potter Road to Franklin Drive
2. Glenlake Drive: Warrington Court to North Gate
3. Stratford Lane: Glenlake Drive to South End
4. Inverness Lane: Winchester Lane to Glenlake Drive
5. Winchester Lane: Inverness Lane to Glenlake Drive
6. Longmeadow Drive: Glenview Road to Lake Avenue
7. Crestwood Lane: Longmeadow to West End
8. Canterbury Lane: East Lake Avenue to South End
9. Sanford Lane: East Lake Avenue to Sanford Court
10. Longmeadow Drive: East Lake Avenue to Bellwood Lane
11. Bellwood Lane: Greenwood Road to Executive Lane
12. Ralmark Lane: Bellwood Lane to Longmeadow Drive
13. Woodmere Lane: Glenview Road to South End

Monday, August 19, 2013

Landscape Restoration On-Going

Last week, the landscaping sub-contractor performed some installation and grading of topsoil and seed at various sites throughout the project. The contractor also completed the repairs at the intersection of Central Road and Shermer Road.

Next week, the contractor is scheduled to complete the remaining asphalt driveway restorations, landscape restorations, and perform pavement markings around the various project sites.

The roadway portion of the project is now on hold until other underground utility work around the Village is completed.

Thank you for your patience and understanding during the construction operations.