The project improvements include:
· Asphalt pavement
· Storm sewer repairs
· Sanitary sewer repairs
· Concrete curb & gutter repair and replacement
. Parkway restoration

Project Timeline:
May 2013 – Start of Construction
October 2013 – End of Construction

Streets scheduled for improvements include:
1. Hammersmith Lane: Potter Road to Franklin Drive
2. Glenlake Drive: Warrington Court to North Gate
3. Stratford Lane: Glenlake Drive to South End
4. Inverness Lane: Winchester Lane to Glenlake Drive
5. Winchester Lane: Inverness Lane to Glenlake Drive
6. Longmeadow Drive: Glenview Road to Lake Avenue
7. Crestwood Lane: Longmeadow to West End
8. Canterbury Lane: East Lake Avenue to South End
9. Sanford Lane: East Lake Avenue to Sanford Court
10. Longmeadow Drive: East Lake Avenue to Bellwood Lane
11. Bellwood Lane: Greenwood Road to Executive Lane
12. Ralmark Lane: Bellwood Lane to Longmeadow Drive
13. Woodmere Lane: Glenview Road to South End

Friday, August 2, 2013

Asphalt Paving on Canterbury and Sanford Completed

Last week, Arrow Road completed grading of the existing base and asphalt paving of binder and surface layers along Sanford and Canterbury.

Next week, Arrow Road is scheduled to pave the asphalt surface layer on Woodmere Lane.

The contractor will also begin landscape and driveway restorations along the project site in the near future.

Once the paving on Woodmere Lane is complete, the roadwork portion of the project will be on hold until other underground utility work around the Village is completed.

Thank you for your patience and understanding during the construction operations.