The project improvements include:
· Asphalt pavement
· Storm sewer repairs
· Sanitary sewer repairs
· Concrete curb & gutter repair and replacement
. Parkway restoration

Project Timeline:
May 2013 – Start of Construction
October 2013 – End of Construction

Streets scheduled for improvements include:
1. Hammersmith Lane: Potter Road to Franklin Drive
2. Glenlake Drive: Warrington Court to North Gate
3. Stratford Lane: Glenlake Drive to South End
4. Inverness Lane: Winchester Lane to Glenlake Drive
5. Winchester Lane: Inverness Lane to Glenlake Drive
6. Longmeadow Drive: Glenview Road to Lake Avenue
7. Crestwood Lane: Longmeadow to West End
8. Canterbury Lane: East Lake Avenue to South End
9. Sanford Lane: East Lake Avenue to Sanford Court
10. Longmeadow Drive: East Lake Avenue to Bellwood Lane
11. Bellwood Lane: Greenwood Road to Executive Lane
12. Ralmark Lane: Bellwood Lane to Longmeadow Drive
13. Woodmere Lane: Glenview Road to South End

Friday, July 26, 2013

Pavement Removal on Sanford, Canterbury, and Woodmere

Last week, Arrow Road completed asphalt pavement removal along Woodmere Lane, Canterbury Lane, and Sanford Lane.  

We anticipated the roadway to be paved mid to late next week, the week of July 29th. The actual timing of the asphalt paving will depend on the amount of repairs needed to be performed once the asphalt pavement is removed.

Thank you for your patience and understanding during the construction operations. Thank you for following the directions detailed in various mailings regarding parking restrictions and access to driveways during the pavement removal and asphalt paving process.