The project improvements include:
· Asphalt pavement
· Storm sewer repairs
· Sanitary sewer repairs
· Concrete curb & gutter repair and replacement
. Parkway restoration

Project Timeline:
May 2013 – Start of Construction
October 2013 – End of Construction

Streets scheduled for improvements include:
1. Hammersmith Lane: Potter Road to Franklin Drive
2. Glenlake Drive: Warrington Court to North Gate
3. Stratford Lane: Glenlake Drive to South End
4. Inverness Lane: Winchester Lane to Glenlake Drive
5. Winchester Lane: Inverness Lane to Glenlake Drive
6. Longmeadow Drive: Glenview Road to Lake Avenue
7. Crestwood Lane: Longmeadow to West End
8. Canterbury Lane: East Lake Avenue to South End
9. Sanford Lane: East Lake Avenue to Sanford Court
10. Longmeadow Drive: East Lake Avenue to Bellwood Lane
11. Bellwood Lane: Greenwood Road to Executive Lane
12. Ralmark Lane: Bellwood Lane to Longmeadow Drive
13. Woodmere Lane: Glenview Road to South End

Friday, June 7, 2013

Concrete Curb & Gutter and Sidewalk Repairs to Begin

Last week, the contractor broke out concrete curb & gutter around structures for adjustments on all the roadways associated with the project and began performing structure adjustments in Glen Lake Estates neighborhood.

Next week, the contractor will begin concrete curb & gutter and sidewalk removal and replacements along Hammersmith Lane, Glenlake Drive, Stratford Lane, Winchester Lane, Inverness Lane, Sanford Lane, and Canterbury Lane. Structure adjustments will continue throughout the roadways within the project. The contractor will also complete the utility improvements along Hammersmith Lane and Winchester Lane.